FORT BENDCOUNTY TOLL ROAD (TEXAS, USA)
Client:FBCTRA, TEXAS. U.S.A.
Concessionaire:Public Entity
Contact Name: MichaelE. Stone, PMP
Phone: (281) 343-0712
Budget: $ 75.5 Million(escalated to 2006 U.S. Dollars)
Execution period:2004 - 2006
Percentageperformed:100%
The Fort Bend County Westpark Toll Road Project is approx. 7.5 miles long and connects SH-99 to the western end of the Harris County WestparkTollway in Fort Bend County, Texas. This project was awarded in 2004 with construction starting in 2004 and ending in 2006. All portions of this toll road are open. The toll road consists of two traffic lanes in each direction, separated by a 2.5´wide concrete barrier, PC concrete pavement structure, lane widths of 12´, 4´ inside, and 10´outside shoulders. Among the important features of this project is the interchange with SH-99.
The construction was performed in 4 phases. Phase A provided the interchange with the North/South section of SH-99 and the toll road. It was built in a period of 18 months and represents approx. 32% of the total work. Phase B begins at .59 miles east of SH-99 and ends .71 miles east of Peek Road. The period of construction was 16 months, representing approx. 29% of the total investment. Phase C started .75 miles east of Mason Rd. and .22 miles west of Long Point Creek ending .45 miles west of FM 1464. This section represents 24% of the total and required a period of 16 months to complete. Phase D was built in a period of 16 months, representing 15% of construction costs. This section began just west of FM 1464 ending just east of the Fort Bend County Line.
| The table at right details the quantities of the major items of work required for the toll road construction. |
| Significant Work Units |
|
Excavation
|
580,051 CY
|
|
Embankment
|
494,467 CY
|
|
Concrete Pavement
|
380,754 SY
|
|
Asphalt
|
27,333 Tn
|
|
Structural Steel
|
1,739,500 Lb
|
|
Drainage Structures
|
61,119 Lf
|
|
|